What material do you choose for walls off grid in
the desert? We looked at dry stack concrete block,
straw bale, adobe, rammed earth, SIPs, CFMs
and stick built to name a few.
Our concerns with straw bale and adobe were
moisture during monsoon season and
labor intentive to construct the walls.
Our land was pretty much flat so rammed
earth would have been out of
the question for us.
SIPs and CFMs seemed to want a contractor
not an owner/builder to contact
them. Stick built we were concerned
about termites, nesting pack rats and
other critters in the desert making
claim to the space in the walls.
We chose dry stack concrete block because
one person (Ron) was building the house.
Although concrete block weighs approximately
27 lbs each, it seemed to be manageable.
The first 5 courses of our off grid dry stack concrete
block were the easiest to lay due to their height.
They went up in a couple of days. Ron was inspired.
Building off grid was proving to be a challenge.
It took
innovative thinking and communicating to each
other our ideas.
Many times we were not very effective. It did prove
to be difficult. We resorted to pictures alot.
Neither of us can draw. It was primitive stick drawings.
In the end, some things came out as invisioned and
some did not. We worked with those that did not.
Ron built staging out of concrete block and 2 X 8's in an effort to minimize climbing up and down ladders for mix and block. That way he just added blocks as the walls were raised.
The metal staging that we had would have to moved to many times to be useful for a one man job. The ground was so unlevel that staging would have been very dangerous.
We had to leave the west side of the house open for the plumbing to be installed. The foundation also had not been poured and it needed to be leveled after the plumber was finished.
So Ron built up the other three sides and the corners of the house. The west side of the house is where the septic and leach field were done.
If you would like to receive updates
please subscribe to JPs E-zine
Go to Surface Bonding Cement from Dry stack
